Borr Data Centre
One of the most advanced and secure data facilities of its kind in Canada, this project set a new standard for reliability, efficiency, and high-security operations.
Plan Group served as the electrical and technology contractor for a Tier 3, high-security data centre in Ottawa. The facility features 750,000 sq. ft. of combined data and office space and was delivered under a Design-Build-Finance-Maintain (DBFM) model.
Our team delivered full electrical and technology systems, including multi-megawatt electrical distribution and generation, uninterruptible power supply (UPS) systems, fire alarms, structured cabling, security, and control systems.
SERVICES
Completed in 2014, this project achieved LEED® Gold certification and was recognized nationally for its scale, complexity, and rigorous security standard.